The second batch production of:
- 56 CROME RACKs (60 have been lunched and 4 have been shifted to batch 3 due to manufacturing issues)
- 49 CROME BULKs (50 have been lunched one has been affected to batch 3 due to manufacturing issues)
is ongoing. The first batch of 25+25 devices have been assembled, tested and calibrated. 23 + 24 are being installed